Construction Update

Construction Update

Follow the progress as the new $22 million Bronson South Haven Hospital takes shape. The two-story, 52,000 square foot facility is located directly east of the existing hospital, facing Blue Star Highway. Construction began in October 2019 and is expected to open in early 2021.

October 3, 2019

  • placeholder1
  • placeholder1
  • placeholder1

December 9, 2019

The weather this fall has cooperated and we're in the process of putting up the steel girders. Soon, the basic shape of the new hospital will be visible.

  • placeholder1
  • placeholder2
  • placeholder2
  • placeholder2

January 9, 2020

The metal framework for the new hospital is nearing completion. The last steel girder is expected to be attached the week of January 20. As seen, some of the outside shell is already in place.

  • placeholder1
  • placeholder2
  • placeholder2
  • placeholder2

February 10, 2020

The new hospital is really taking shape! Work continues to get the new structure enclosed and weatherproofed.

  • placeholder1
  • placeholder2
  • placeholder2
  • placeholder2

March 12, 2020

With the structure enclosed, work begins on the inside of the building. As you can see, the second floor is already in place.

  • placeholder1
  • placeholder2
  • placeholder2
  • placeholder2

April 14, 2020

We start with an aerial view, showing most of the new hospital enclosed. You can also see the brick facade of the hospital in progress. Inside, the installation of the wall studs begins.

  • placeholder1
  • placeholder2
  • placeholder2
  • placeholder2

August 13, 2020

The new construction of the new hospital is really coming along. Take a look at the photo of the spacious, window-filled lobby that was taken from the second floor. The fourth photo shows some of the second floor exam rooms taking shape.

  • placeholder1
  • placeholder2
  • placeholder2
  • placeholder2

September 14, 2020

Construction work on the exterior brick and porcelain facade has been completed and the new hospital is really taking shape. Metal panel work and canopy finish details are in progress. The first layer of asphalt for the driveway and parking lot are currently being laid with the final layer planned for late fall. Interior work has moved to flooring, cabinetry and painting in most of the exam rooms on the second floor. Drywall work is happening in tandem with electrical and data installs on the first floor.

  • placeholder1
  • placeholder2
  • placeholder2
  • placeholder2

February 18, 2021

Lots of finish work is being completed on the interior of the new hospital. We are excited to see everything come together and can't wait to open the new hospital to the community.

  • The lobby from the second floor
  • Inpatient room
  • main hallway first floor
  • Second floor nurse station

Like our Facebook page to follow what is happening right now at Bronson South Haven.

Facebook icon.

Find a Doctor Icon

Looking for a Bronson doctor?
Find the perfect fit for you.

Find a Doctor

Bronson Health News

Get the latest health news, tips and trends from Bronson.

South haven e-news

See the latest news

Icon of a hand holding a heart-shaped token.

Help Bronson support our community with a monetary donation.

Donate today

Related Classes at Bronson South Haven Hospital